NS-34 - Thermal Power Project with Capacity and Efficiency Increase II - TTP Nikola Tesla – Unit A3

Serbia

NAMA Seeking Support for Implementation

  • A Overview
    • A.1Party
      A.2Title of Mitigation Action
      A.3Description of mitigation action
      Restoration and modernization of a lignite thermal power plant with capacity increase of 30 MW. Adopted technologies are rehabilitation and modernization of the steam turbine, condensing plant and cooling system unit, boiler and auxiliary equipment (e.g., low/high pressure feed water heaters), as well as revitalization and improvement of the firing system and the combustion process by introducing "Low NOx" burners and increasing the efficiency of the old thermal units.
      A.4Sector





      A.5Technology









      A.6Type of action




      A.7Greenhouse gases covered by the action




  • B National Implementing Entity
    • B.1.0Name
      B.1.1Contact Person 1
      B.1.2Address
      B.1.3Phone
      B.1.4Email
      B.1.5Contact Person 2
      B.1.6Address
      B.1.7Phone
      B.1.8Email
      B.1.9Contact Person 3
      B.1.10Address
      B.1.11Phone
      B.1.12Email
      B.1.13Comments
      B.2.0Name
      B.2.1Contact Person 1
      B.2.2Address
      B.2.3Phone
      B.2.4Email
      B.2.5Contact Person 2
      B.2.6Address
      B.2.7Phone
      B.2.8Email
      B.2.9Contact Person 3
      B.2.10Address
      B.2.11Phone
      B.2.12Email
      Add Additional Entity
  • C Expected timeframe for the implementation of the mitigation action
    • C.1Number of years for completion
      C.2Expected start year of implementation
  • D Currency
    • D.1Used Currency
      Conversion to USD: 1
  • E Cost
    • E.1.1Estimated full cost of implementation
      Conversion to USD: 60,802,070
      E.1.2Comments on full cost of implementation
      E.2.1Estimated incremental cost of implementation
      Conversion to USD: 0
      E.2.2Comments on estimated incremental cost of implementation
  • F Support required for the implementation the mitigation action
    • F.1.1Amount of Financial support
      Conversion to USD: 60,802,070
      F.1.2Type of required Financial support





      F.1.3Comments on Financial support
      EPS is open for various solutions regarding the finance of the project as stated in F.1.2.
      F.2.1Amount of Technological support
      F.2.2Comments on Technological support
      F.3.1Amount of capacity building support
      Conversion to USD: 0
      F.3.2Type of required capacity building support


      F.3.3Comments on Capacity Building support
  • G Estimated emission reductions
    • G.1Amount
      G.2Unit
      G.3Additional imformation (e.g. if available, information on the methodological approach followed)
      Estimation is calculated based on 15 years of technical life time of instalation after the reconstruction.
  • H Other indicators
    • H.1Other indicators of implementation
      Idea Design and Feasibility Study is under development
  • I Other relevant information
    • I.1Other relevant information including co-benefits for local sustainable development
      Implementation of the NAMA is meeting majority of the Sustainable Development Indicators in accordance with tree criterion indicated in appendix of the Serbian DNA Rules of procedure. According to the economic criterion, it satisfies following fields: 1. Economic development of the region - Reconstruction of the TPP Nikola Tesla A3 will improve ehisting infrastructure; it also contributes to the power system stability and supply security, which consequently have effect on the stability of the prices for electric energy. 2. Employment - Reconstruction of the TPP Nikola Tesla A3 will provide work for many domestic companies. 3. Priorities of the sector - Power generation at the TPP Nikola Tesla A3 will contribute to the power system stability and supply security, which represent one of the priorities in the energy sector. 4. Consumption and generation - Power generation at the reconstructed power plant will reduce need for electricity import, and its modern concept will reduce waste production per unit of generated energy as well as waste management in ecology acceptable manner. According to the social criterion, it satisfies following fields: 1. Life conditions improvement - Project implementation of such scope, lead up to the employment increase, as well as income increase, on the local and regional level. 2. Capacity increase - According to the work needs and modern equipment maintenance, strategic partner will provide training for the employees, as well as expertise and tools for local companies engaged on this implementation of the project during its operational life. According to the environment and natural resources criterions, it satisfies following fields: 1. Energy resources – Generation of TPP Nikola Tesla A3 will, due to the higher energy efficiency of the plant, reduce coal consumption for power generation, and significantly reduce need for electricity import. 2. Air - Due to the application of the modern technology and higher energy efficiency of the plant, project will result in reduced emission levels of CO2, SOx and NOx, comparing to the existing thermo power plants in Serbia. 3. Water - Contribution to the sustainable water use would be the application of measures for water treatment of all water quantities used in the technological process of electricity generation. TENT_A3 4 / 4 6. Natural recourses - Modern concept of the unit TPP Nikola Tesla A3 will significantly contribute to the sustainable use of mineral recourses, because energy efficiency of primary energy transformation (≈ 34%) will be significantly higher than existing thermal power plants in Serbia. Exploitation life of domestic lignite deposits is extended that way.
  • J Relevant National Policies strategies, plans and programmes and/or other mitigation action
    • J.1Relevant National Policies
      http://www.merz.gov.rs/en ; http://192.168.16.144/Eng/Article.aspx?lista=Sitemap&id=14
      J.2Link to other NAMAs
  • K Attachments
  • L Support received
    • L.1Outside the Registry
      L.2Within the Registry
      Support providedSupportTypeAmountCommentDate
      No records to display.