Skip Ribbon Commands
Skip to main content

Public NAMA

:

My Application Page

NS-192 - Solar electric power plant

Syrian Arab Republic

NAMA Seeking Support for Implementation

  • A Overview
    • A.1Party
      A.2Title of Mitigation Action
      A.3Description of mitigation action
      installation of Solar electric power plant with capacity of 1 MW within the conversion station of AlKiswah area near Damascus.
      A.4Sector





      A.5Technology









      A.6Type of action




      A.7Greenhouse gases covered by the action




  • B National Implementing Entity
    • B.1.0Name
      B.1.1Contact Person 1
      B.1.2Address
      B.1.3Phone
      B.1.4Email
      B.1.5Contact Person 2
      B.1.6Address
      B.1.7Phone
      B.1.8Email
      B.1.9Contact Person 3
      B.1.10Address
      B.1.11Phone
      B.1.12Email
      B.1.13Comments
      B.2.0Name
      B.2.1Contact Person 1
      B.2.2Address
      B.2.3Phone
      B.2.4Email
      B.2.5Contact Person 2
      B.2.6Address
      B.2.7Phone
      B.2.8Email
      B.2.9Contact Person 3
      B.2.10Address
      B.2.11Phone
      B.2.12Email
      Add Additional Entity
  • C Expected timeframe for the implementation of the mitigation action
    • C.1Number of years for completion
      C.2Expected start year of implementation
  • D Currency
    • D.1Used Currency
      Conversion to USD: 1
  • E Cost
    • E.1.1Estimated full cost of implementation
      Conversion to USD: 1,293,661
      E.1.2Comments on full cost of implementation
      E.2.1Estimated incremental cost of implementation
      Conversion to USD: 0
      E.2.2Comments on estimated incremental cost of implementation
  • F Support required for the implementation the mitigation action
    • F.1.1Amount of Financial support
      Conversion to USD: 1,293,661
      F.1.2Type of required Financial support





      F.1.3Comments on Financial support
      F.2.1Amount of Technological support
      F.2.2Comments on Technological support
      F.3.1Amount of capacity building support
      Conversion to USD: 0
      F.3.2Type of required capacity building support


      F.3.3Comments on Capacity Building support
  • G Estimated emission reductions
    • G.1Amount
      G.2Unit
      G.3Additional imformation (e.g. if available, information on the methodological approach followed)
  • H Other indicators
    • H.1Other indicators of implementation
  • I Other relevant information
    • I.1Other relevant information including co-benefits for local sustainable development
  • J Relevant National Policies strategies, plans and programmes and/or other mitigation action
    • J.1Relevant National Policies

      The Contract system No. 51/2004

      The investment plans( Five-Year Plans.. )

      The national Comprehensive development programs

      Environmental Law No 12/2012

      J.2Link to other NAMAs
  • K Attachments
  • L Support received
    • L.1Outside the Registry
      L.2Within the Registry
      Support providedSupportTypeAmountCommentDate
      No records to display.
Download page as PDF file